- Question #351
As a result of changes in the economy, it has been communicated that the current costs for needed components have doubled from what was originally budgeted. If the procurement occu...
- Question #352
A project needs software. After analyzing the choices, it is determined that if made in- house, it will cost $100,000. However, if the software is purchased, the cost would be $25,...
- Question #353
Determining how to communicate general project information with a globally dispersed team has created scheduling challenges. Which of the following would BEST remedy the situation?
- Question #354
A project manager is using historical data from multiple projects to estimate activity durations. Which of the following network diagrams would BEST allow for the utilization of th...
- Question #355
Upper and lower control limits could be set at a standard deviation of three. Which of the following represents the associated confidence level?
- Question #356
When looking for solutions, which of the following procurement documents should be used?
- Question #357
While working on a project, an unforeseen event arises that impacts a project objective. Which of the following should be updated as a result?
- Question #358
While working on a project, a workaround is implemented to deal with an unforeseen event. Which of the following should be the NEXT step?
- Question #359
Objectives contained in the charter should resolve the:
- Question #360
An organization with a matrix structure typically:
- Question #361
The formula for Schedule Performance Index (SPI) is:
- Question #362
Schedule dependenciesinclude:(Select TWO).
- Question #363
The primary purpose for documenting lessons learned during project closure is to:
- Question #364
A common agenda item in a project kick-off meeting should include which of the following?
- Question #365
A project's Critical Path is:
- Question #366
Which of the following conflict resolution techniques results in a lose-lose scenario?
- Question #367
Which of the following types of risk responses would an insurance policy describe?
- Question #368
The project is running behind schedule because one of the developers has taken an unscheduled vacation. The project manager informs the developer that any further unauthorized abse...
- Question #369
During the execution phase of a project, a change request has been approved to add activities to the critical path without altering the schedule. Which of the following techniques...
- Question #370
A customer is reporting that the projects deliverables are not meeting the acceptance criteria. Which of the following documents MOST likely needs to be updated?
- Question #371
During the execution of an assigned task the developer informs the project manager of a missing component. Which of the following should the project manager do next?
- Question #372
A project manager creates a detailed list of costs for each activity involved in the project and then uses the sum of the individual activities to create the budget. Which of the f...
- Question #373
Which of the following estimating techniques is the MOST accurate?
- Question #374
Which of the following could be identified as a main stakeholder in any project?
- Question #375
A team member is not happy to be assigned to a certain project manager's project. The team member has been communicating displeasure to the rest of the project team. Which of the f...
- Question #376
A quality assurance process should include:
- Question #377
Administrative closure of a project includes which of the following activities?
- Question #378
The project manager can use the lowest level of the risk breakdown structure (RBS) to create which of the following documents?
- Question #379
Which of the following are components of an internal / external communication plan? (Select Two).
- Question #380
Which of the following is the definition of compromising?
- Question #381
Which of the following actions would require a formal project closure? (Select Two).
- Question #382
The lessons-learned activity and formal acceptance documentation form part of which of the following process groups?
- Question #383
Which of the following documents is used when soliciting vendors?
- Question #384
Which of the following components is included in a transition plan?
- Question #385
A customer requests that the products quality be reduced to control its cost. Which of the following actions should the project manager take FIRST?
- Question #386
Which of the following components are included in a communication plan? (Select Two).
- Question #387
A project budget has been reduced by 10 percent, but the project has a critical deadline. Which of the following should the project manager do FIRST to complete the project on time...
- Question #388
Key resources on a project are being shared. The stakeholders are aware of the shared resources and do not expect this to impact the progress of the project. In which of the follow...
- Question #389
Several key resources will be unavailable at the end of the project. The key stakeholders want to outsource the project to a third party. Which of the following risk responses is d...
- Question #390
Several managers are sharing a project team member, which is impacting the progress of both projects. Which of the following BEST describes the situation?
- Question #391
Which of the following occurs during a project kick-off meeting? (Select Two).
- Question #392
A project manager has failed to obtain the necessary permits from the local building commission. The project has been stopped because of a failure to understand the importance of:
- Question #393
Which of the following should be created in the project closing documentation? (Select Two).
- Question #394
A project can be defined as which of the following?
- Question #395
Which of the following elements would be needed to prepare an effective project scope document?
- Question #396
In which of the following organization types is it LEAST likely that a conflict regarding competing demands for resources would take place?
- Question #397
Which of the following elements does a project charter contain?
- Question #398
Which of the following describes the point in time when resources can be assigned to scheduled tasks?
- Question #399
During which of the following process groups is the preliminary project risk assessment performed?
- Question #400
Which of the following is a use for a Pareto diagram?