PK0-003 · Question #399
During which of the following process groups is the preliminary project risk assessment performed?
The correct answer is B. Planning. The preliminary project risk assessment is performed during the Planning process group, where risks are identified, analyzed, and prioritized.
Question
During which of the following process groups is the preliminary project risk assessment performed?
Options
- AMonitoring/Controlling
- BPlanning
- CInitiating
- DExecuting
How the community answered
(45 responses)- A2% (1)
- B89% (40)
- C2% (1)
- D7% (3)
Why each option
The preliminary project risk assessment is performed during the Planning process group, where risks are identified, analyzed, and prioritized.
The Monitoring/Controlling process group involves tracking existing risks, identifying new ones, and evaluating the effectiveness of risk responses, not the initial preliminary assessment.
The preliminary project risk assessment is primarily performed during the Planning process group, where risks are systematically identified, analyzed, and prioritized. This allows the project team to develop appropriate risk response strategies and incorporate them into the project management plan before execution begins.
While high-level risks might be mentioned in the Initiating phase, a detailed 'preliminary risk assessment' with analysis and planning occurs during the Planning process group.
The Executing process group focuses on carrying out the project work and implementing risk response plans, rather than performing the initial comprehensive risk assessment.
Concept tested: Project management process groups and risk assessment
Source: https://www.pmi.org/learning/library/risk-management-project-planning-7212