nerdexam
CompTIA

PK0-003 · Question #362

Schedule dependenciesinclude:(Select TWO).

The correct answer is A. Successor activities D. Predecessor activities. Schedule dependencies are relationships between project activities, defining the order in which they must or can be performed.

Project life cycle phases

Question

Schedule dependenciesinclude:(Select TWO).

Options

  • ASuccessor activities
  • BRisks
  • CConstraints
  • DPredecessor activities
  • EIssues
  • FAssumptions

How the community answered

(20 responses)
  • A
    90% (18)
  • B
    5% (1)
  • F
    5% (1)

Why each option

Schedule dependencies are relationships between project activities, defining the order in which they must or can be performed.

ASuccessor activitiesCorrect

Successor activities are tasks that cannot start or finish until another activity (their predecessor) has started or finished, establishing a direct dependency in the schedule.

BRisks

Risks are uncertain events that may affect the project schedule, but they are not inherent schedule dependencies themselves.

CConstraints

Constraints are limitations or restrictions that affect project scheduling, such as fixed dates or resource availability, but they are not activities that define dependencies.

DPredecessor activitiesCorrect

Predecessor activities are tasks that must be completed or started before another activity (their successor) can begin or finish, creating a fundamental schedule dependency.

EIssues

Issues are problems that have occurred and require resolution, which can impact the schedule but are not fundamental dependency types.

FAssumptions

Assumptions are factors believed to be true for planning purposes, which can influence the schedule but are not direct activity-to-activity dependencies.

Concept tested: Project schedule activity dependencies

Source: https://www.projectmanager.com/blog/what-is-project-dependency

Topics

#Schedule management#Activity sequencing#Dependencies#Predecessor activities

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice