PK0-003 · Question #381

Which of the following actions would require a formal project closure? (Select Two).

The correct answer is C. The project work is completed. D. The project has run out of money.. Formal project closure is required when a project successfully completes its objectives or is terminated prematurely due to critical issues. Both successful completion and termination events necessitate documenting the project's end and releasing resources.

Project life cycle phases

Question

Which of the following actions would require a formal project closure? (Select Two).

Options

  • AThe project is delayed indefinitely because a required vendor part cannot be delivered.
  • BThe project is producing a product that is no longer compliant with new Federal regulations.
  • CThe project work is completed.
  • DThe project has run out of money.
  • EThe project sponsor has become disinterested in the project.

How the community answered

(53 responses)
  • A
    4% (2)
  • B
    4% (2)
  • C
    91% (48)
  • E
    2% (1)

Why each option

Formal project closure is required when a project successfully completes its objectives or is terminated prematurely due to critical issues. Both successful completion and termination events necessitate documenting the project's end and releasing resources.

AThe project is delayed indefinitely because a required vendor part cannot be delivered.

An indefinite delay due to a vendor issue might eventually lead to a decision to terminate the project, but the delay itself is not the formal closure action; the decision to terminate would trigger closure.

BThe project is producing a product that is no longer compliant with new Federal regulations.

Producing a non-compliant product indicates a failure in project output that would likely necessitate re-scoping, corrective actions, or project termination, but the non-compliance itself is not the formal closure event.

CThe project work is completed.Correct

When all project work is completed and its objectives are achieved, formal closure is necessary to officially acknowledge the project's conclusion, gain final stakeholder acceptance, and release project resources.

DThe project has run out of money.Correct

Running out of money constitutes a critical project termination event, requiring formal project closure to cease activities, document the reasons for financial cessation, and settle all outstanding accounts and contracts.

EThe project sponsor has become disinterested in the project.

A disinterested project sponsor might signal a lack of executive support, potentially leading to project termination, but their disinterest alone is not the formal trigger for project closure; the subsequent decision to terminate is.

Concept tested: Project closure triggers and conditions

Topics

#Project closure#Project termination conditions#Project life cycle