PK0-003 · Question #384
Which of the following components is included in a transition plan?
The correct answer is A. Ownership. A transition plan is crucial for successfully handing over a project's deliverables to operational teams, ensuring clear responsibilities and support for the new system or service. Defining ownership is a core component to ensure accountability post-project.
Question
Which of the following components is included in a transition plan?
Options
- AOwnership
- BQuality metrics
- CProject budget
- DQuality baseline
How the community answered
(48 responses)- A92% (44)
- B4% (2)
- C2% (1)
- D2% (1)
Why each option
A transition plan is crucial for successfully handing over a project's deliverables to operational teams, ensuring clear responsibilities and support for the new system or service. Defining ownership is a core component to ensure accountability post-project.
A transition plan details how a project's deliverables will be moved into an operational state, and a key component is establishing clear ownership, including roles and responsibilities, for the ongoing support, maintenance, and management of the new system or service.
Quality metrics are used to measure the quality of project processes and deliverables during the project's execution and monitoring phases, not as a core component of the transition plan itself.
The project budget outlines the financial resources allocated for the project's execution and is part of the overall project plan, rather than a specific component included within the transition plan.
A quality baseline defines the acceptable level of quality for project deliverables and is established during the project planning phase, not as a component within the transition plan.
Concept tested: Project transition plan components
Source: https://learn.microsoft.com/en-us/azure/architecture/guide/developer/governance-process-developer-transition-plan