PK0-003 · Question #11

A project manager is recording the probability and impact of an uncertain event. Which of the following would be the BEST document to capture this data?

The correct answer is C. Risk register. The risk register is the definitive project document for systematically capturing and analyzing information about potential future risks. It details risk probability, impact, and planned responses.

Tools and documentation

Question

A project manager is recording the probability and impact of an uncertain event. Which of the following would be the BEST document to capture this data?

Options

  • AIssues log
  • BResponsibility assignment matrix
  • CRisk register
  • DActivity log

How the community answered

(43 responses)
  • A
    2% (1)
  • B
    5% (2)
  • C
    91% (39)
  • D
    2% (1)

Why each option

The risk register is the definitive project document for systematically capturing and analyzing information about potential future risks. It details risk probability, impact, and planned responses.

AIssues log

An issues log tracks problems that have already occurred or are currently ongoing, not uncertain future events.

BResponsibility assignment matrix

A responsibility assignment matrix (e.g., RACI) clarifies who is responsible for specific tasks or deliverables, not for capturing risk data.

CRisk registerCorrect

The risk register is the primary document used in project management to record identified risks, including their probability, potential impact, priority, and planned response strategies.

DActivity log

An activity log typically records tasks performed or completed, not the probability and impact of uncertain future events.

Concept tested: Project risk management documentation

Source: https://learn.microsoft.com/en-us/dynamics365/project-operations/pm/project-risk-management

Topics

#risk management#risk register#probability and impact