PK0-003 · Question #276

Which of the following would be found in a transition plan? (Select TWO).

The correct answer is C. Training requirements E. Extended support. A transition plan focuses on moving the project deliverables into operational use, detailing essential elements such as training requirements for end-users and provision for extended support post-handover.

Tools and documentation

Question

Which of the following would be found in a transition plan? (Select TWO).

Options

  • AKey milestones
  • BProject acceptance criteria
  • CTraining requirements
  • DTollgate approvals
  • EExtended support

How the community answered

(29 responses)
  • A
    3% (1)
  • C
    93% (27)
  • D
    3% (1)

Why each option

A transition plan focuses on moving the project deliverables into operational use, detailing essential elements such as training requirements for end-users and provision for extended support post-handover.

AKey milestones

Key milestones are significant points in the project schedule, typically found in the project schedule or project plan, not specifically the transition plan, which focuses on post-delivery.

BProject acceptance criteria

Project acceptance criteria define the conditions that must be met for the project deliverables to be accepted by the customer or sponsor, generally part of the scope statement or project charter, prior to transition.

CTraining requirementsCorrect

Training requirements are a crucial component of a transition plan, ensuring that end-users, support staff, or operational teams are adequately prepared to use, maintain, or manage the new product or system being delivered.

DTollgate approvals

Tollgate approvals are decision points within the project lifecycle where management reviews progress and decides whether to continue to the next phase, which is part of overall project governance, not the transition plan content.

EExtended supportCorrect

Extended support provisions, including details on ongoing maintenance, service level agreements (SLAs), and contact information for post-implementation issues, are vital elements of a transition plan to ensure long-term operational success after project completion.

Concept tested: Contents of a project transition plan

Topics

#transition plan#training requirements#extended support