PK0-003 · Question #277

Exploiting is considered to be a response of which of the following?

The correct answer is A. Risk opportunity. Exploiting is a risk response strategy used to maximize the probability and impact of positive risks, also known as opportunities.

Project management concepts

Question

Exploiting is considered to be a response of which of the following?

Options

  • ARisk opportunity
  • BConflict resolution technique
  • CRisk threat
  • DResource leveling technique

How the community answered

(60 responses)
  • A
    88% (53)
  • B
    2% (1)
  • C
    7% (4)
  • D
    3% (2)

Why each option

Exploiting is a risk response strategy used to maximize the probability and impact of positive risks, also known as opportunities.

ARisk opportunityCorrect

Exploiting is a risk response strategy for opportunities, where the organization takes active steps to ensure a positive risk event occurs and its benefits are fully realized. This involves allocating resources or taking actions to make the opportunity happen.

BConflict resolution technique

Conflict resolution techniques are methods for resolving disagreements between stakeholders, not for responding to project risks.

CRisk threat

Exploiting is a response to an opportunity (positive risk), not a threat (negative risk), which would typically be avoided, mitigated, or transferred.

DResource leveling technique

Resource leveling techniques are used to adjust the project schedule to optimize resource allocation and availability, not to respond to risks.

Concept tested: Risk response strategies for opportunities