PK0-003 · Question #150
Which of the following does the Critical Path tell the Project Manager? (Select TWO).
The correct answer is B. The earliest completion for project work E. The longest series of activities. The Critical Path method identifies the longest sequence of dependent activities in a project, determining the earliest possible completion date for the entire project.
Question
Which of the following does the Critical Path tell the Project Manager? (Select TWO).
Options
- AWhere potential delays in the project might occur
- BThe earliest completion for project work
- CActivities that can be done in parallel
- DThe allocation time for each person assigned to the project
- EThe longest series of activities
How the community answered
(18 responses)- B94% (17)
- C6% (1)
Why each option
The Critical Path method identifies the longest sequence of dependent activities in a project, determining the earliest possible completion date for the entire project.
While the critical path highlights activities with zero float, making them susceptible to delays, this is an implication rather than what the critical path directly "tells" as its primary output; its primary outputs are duration and sequence.
The Critical Path identifies the sequence of activities that dictates the shortest possible project duration, thereby revealing the earliest completion date for the entire project. This is achieved by summing the durations of all activities along this longest path.
The critical path identifies sequential activities that must be completed in order, not activities that can be done in parallel (which are typically off the critical path or represent independent paths).
Resource allocation time is part of resource management and scheduling, but not a direct output or primary function of the Critical Path method itself.
The Critical Path is defined as the longest sequence of activities in the project schedule network diagram, with the least amount of float or slack, establishing the minimum time required to complete the project. This path determines the overall project duration and guides scheduling.
Concept tested: Critical Path Method (CPM) understanding