A project manager has been asked to create an issues log. Which of the following should be included in the issues log? (Select TWO).
The correct answer is A. The description of the issue D. The date the issue was submitted. An issues log should document key details about problems encountered, including a clear description of the issue and the date it was officially submitted.
Question
A project manager has been asked to create an issues log. Which of the following should be included in the issues log? (Select TWO).
Options
- AThe description of the issue
- BThe cost of the issue
- CThe risk log
- DThe date the issue was submitted
- EThe work breakdown structure (WBS)
How the community answered
(20 responses)- A90% (18)
- C5% (1)
- E5% (1)
Why each option
An issues log should document key details about problems encountered, including a clear description of the issue and the date it was officially submitted.
A description of the issue is crucial for understanding the problem, its nature, and its potential impact, enabling effective tracking and resolution.
While an issue might eventually have a cost impact, 'the cost of the issue' itself is typically an outcome or an estimated impact, not a primary, inherent piece of information to be included as a core field when initially logging an issue.
An issues log is distinct from a risk log; while issues can arise from risks, the risk log itself is a separate document for managing potential future events.
Recording the date the issue was submitted provides a clear timestamp, which is essential for tracking resolution timelines, prioritizing issues, and auditing the project's progress.
The work breakdown structure (WBS) is a hierarchical decomposition of project deliverables and tasks, not a component to be directly included within an issues log.
Concept tested: Contents of an issues log