Which of the following are tools used in quality control? (Select TWO).
The correct answer is B. Ishikawa diagram E. Pareto chart. Ishikawa diagrams (fishbone diagrams) and Pareto charts are quality control tools used to identify root causes of defects and prioritize issues, respectively.
Question
Which of the following are tools used in quality control? (Select TWO).
Options
- AGantt chart
- BIshikawa diagram
- CParametric estimating
- DProbability and impact matrix
- EPareto chart
How the community answered
(48 responses)- A2% (1)
- B94% (45)
- D4% (2)
Why each option
Ishikawa diagrams (fishbone diagrams) and Pareto charts are quality control tools used to identify root causes of defects and prioritize issues, respectively.
A Gantt chart is a project schedule management tool used for planning and tracking tasks, not primarily for quality control.
An Ishikawa diagram, also known as a fishbone or cause-and-effect diagram, is a quality control tool used to visually identify and categorize the potential causes of a problem or defect.
Parametric estimating is a cost or duration estimating technique that uses historical data and mathematical algorithms, not a quality control tool.
A probability and impact matrix is a risk management tool used for assessing and prioritizing risks, not for quality control.
A Pareto chart is a quality control tool that displays defects or causes in descending order of frequency or impact, helping to identify the "vital few" problems that need attention.
Concept tested: Quality management - quality control tools
Source: https://www.projectmanager.com/blog/quality-control-tools-techniques