Which of the following are included in a risk register? (Select TWO).

The correct answer is A. Project risk responses B. Identified risks. A risk register is a central repository for documenting all identified project risks and outlining their corresponding response plans.

Tools and documentation

Question

Which of the following are included in a risk register? (Select TWO).

Options

  • AProject risk responses
  • BIdentified risks
  • CMajor milestones
  • DRisk analysis tools
  • ERisk control board members

How the community answered

(16 responses)
  • A
    94% (15)
  • D
    6% (1)

Why each option

A risk register is a central repository for documenting all identified project risks and outlining their corresponding response plans.

AProject risk responsesCorrect

For each identified risk, the risk register includes planned risk responses, which detail the actions to be taken to mitigate, avoid, transfer, or accept the risk.

BIdentified risksCorrect

Identified risks are a fundamental component of a risk register, detailing potential future events that could impact project objectives and requiring active management.

CMajor milestones

Major milestones are part of the project schedule and project plan, not typically a direct entry within the risk register, though their delay could be an identified risk.

DRisk analysis tools

Risk analysis tools are methods or software used to perform risk analysis, but they are not recorded as content within the risk register itself.

ERisk control board members

Risk control board members are individuals or roles involved in the governance of risks, and their names or roles are not usually listed as entries in the risk register.

Concept tested: Risk register components in project management

Topics

#risk management#risk register#risk responses