PK0-003 · Question #285
Which of the following are included in a risk register? (Select TWO).
The correct answer is A. Project risk responses B. Identified risks. A risk register is a central repository for documenting all identified project risks and outlining their corresponding response plans.
Question
Which of the following are included in a risk register? (Select TWO).
Options
- AProject risk responses
- BIdentified risks
- CMajor milestones
- DRisk analysis tools
- ERisk control board members
How the community answered
(16 responses)- A94% (15)
- D6% (1)
Why each option
A risk register is a central repository for documenting all identified project risks and outlining their corresponding response plans.
For each identified risk, the risk register includes planned risk responses, which detail the actions to be taken to mitigate, avoid, transfer, or accept the risk.
Identified risks are a fundamental component of a risk register, detailing potential future events that could impact project objectives and requiring active management.
Major milestones are part of the project schedule and project plan, not typically a direct entry within the risk register, though their delay could be an identified risk.
Risk analysis tools are methods or software used to perform risk analysis, but they are not recorded as content within the risk register itself.
Risk control board members are individuals or roles involved in the governance of risks, and their names or roles are not usually listed as entries in the risk register.
Concept tested: Risk register components in project management
Topics
Community Discussion
No community discussion yet for this question.