PK0-003 · Question #194
A key stakeholder has requested a change to the delivery frequency of the risk register. Which of the following documents should be updated?
The correct answer is A. Communications Plan. A stakeholder's request to change the delivery frequency of the risk register concerns how project information is communicated. The document that defines these communication details is the Communications Plan.
Question
A key stakeholder has requested a change to the delivery frequency of the risk register. Which of the following documents should be updated?
Options
- ACommunications Plan
- BRisk Register
- CWork Breakdown Structure
- DChange Log
How the community answered
(28 responses)- A82% (23)
- B4% (1)
- C4% (1)
- D11% (3)
Why each option
A stakeholder's request to change the delivery frequency of the risk register concerns how project information is communicated. The document that defines these communication details is the Communications Plan.
The Communications Plan explicitly outlines how project information, including the frequency and methods of delivering reports like the risk register, will be shared with stakeholders. Therefore, any change to a report's delivery frequency necessitates an update to this plan.
The Risk Register contains details about identified risks, their analysis, and responses, but it does not specify its own distribution frequency.
Concept tested: Project Communications Management updates