nerdexam
ExamsPK0-003Questions#193
CompTIA

PK0-003 · Question #193

PK0-003 Question #193: Real Exam Question with Answer & Explanation

The correct answer is B: Submit an RFQ to find a less expensive material.. See the full explanation below for the reasoning.

Question

The project manager has been informed the project's CPI is 0.85 on a multi-year project that is 30% complete. Which of the following actions would be BEST for the project manager to take?

Options

  • AAsk the project sponsor to extend the project schedule.
  • BSubmit an RFQ to find a less expensive material.
  • CAssign additional team members to Quality Control.
  • DFast track the project to reduce risk.

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice
The project manager has been informed the project's CPI is 0.85 on... | PK0-003 Q#193 Answer | NerdExam