CompTIA
PK0-003 · Question #193
PK0-003 Question #193: Real Exam Question with Answer & Explanation
The correct answer is B: Submit an RFQ to find a less expensive material.. See the full explanation below for the reasoning.
Question
The project manager has been informed the project's CPI is 0.85 on a multi-year project that is 30% complete. Which of the following actions would be BEST for the project manager to take?
Options
- AAsk the project sponsor to extend the project schedule.
- BSubmit an RFQ to find a less expensive material.
- CAssign additional team members to Quality Control.
- DFast track the project to reduce risk.
Community Discussion
No community discussion yet for this question.