The customer now needs the project's deliverable 3 months earlier than scheduled. The deliverable's quality has been reduced so the budget will not be impacted. Which of the following does the project

The correct answer is D. Schedule. The customer's new requirement to receive the project's deliverable three months earlier directly impacts the project's timeline. The project schedule is the primary document that defines these time-related aspects.

Project management concepts

Question

The customer now needs the project's deliverable 3 months earlier than scheduled. The deliverable's quality has been reduced so the budget will not be impacted. Which of the following does the project manager need to update?

Options

  • AIssues Log
  • BCommunications Plan
  • CProject budget
  • DSchedule

How the community answered

(65 responses)
  • A
    9% (6)
  • B
    5% (3)
  • C
    3% (2)
  • D
    83% (54)

Why each option

The customer's new requirement to receive the project's deliverable three months earlier directly impacts the project's timeline. The project schedule is the primary document that defines these time-related aspects.

AIssues Log

An Issues Log is used to record problems or obstacles that require resolution, not to document a requested change to the project timeline.

BCommunications Plan
CProject budget
DScheduleCorrect

The project schedule is the document that details the planned start and end dates for project activities and deliverables. Accelerating a deliverable's completion by three months is a direct and significant change to the project's timeline, necessitating an update to the schedule.

Concept tested: Project Schedule Management updates

Topics

#Project schedule#Change management#Project constraints

Community Discussion

No community discussion yet for this question.