nerdexam
ExamsPK0-003Questions#195
CompTIA

PK0-003 · Question #195

PK0-003 Question #195: Real Exam Question with Answer & Explanation

The correct answer is D: Schedule. See the full explanation below for the reasoning.

Question

The customer now needs the project's deliverable 3 months earlier than scheduled. The deliverable's quality has been reduced so the budget will not be impacted. Which of the following does the project manager need to update?

Options

  • AIssues Log
  • BCommunications Plan
  • CProject budget
  • DSchedule

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice
The customer now needs the project's deliverable 3 months earlier... | PK0-003 Q#195 Answer | NerdExam