Question
The customer now needs the project's deliverable 3 months earlier than scheduled. The deliverable's quality has been reduced so the budget will not be impacted. Which of the following does the project manager need to update?
Options
- AIssues Log
- BCommunications Plan
- CProject budget
- DSchedule