CompTIA
PK0-003 · Question #196
PK0-003 Question #196: Real Exam Question with Answer & Explanation
Sign in or unlock PK0-003 to reveal the answer and full explanation for question #196. The question stem and answer options stay visible for context.
Question
The customer has agreed to pay 20% more for the project deliverable if it can be turned over to them in four weeks. The project manager has the team members to complete the project, but is having difficulty procuring enough material from a vendor. The project manager agrees to pay 5% more for the material if complete shipment can be made within a week. This is an example of which of the following risk response strategies?
Options
- ATransferring
- BEnhancing
- CSharing
- DExploiting
Unlock PK0-003 to see the answer
You've previewed enough free PK0-003 questions. Unlock PK0-003 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.