PK0-003 · Question #197

A project is having issues because the team is unclear what they should be doing and who should be doing it. This could have been avoided by using:

The correct answer is C. Acommunication plan.. The project team is confused about roles and tasks, indicating a failure in clearly disseminating information about responsibilities and activities.

Tools and documentation

Question

A project is having issues because the team is unclear what they should be doing and who should be doing it. This could have been avoided by using:

Options

  • AArisk register.
  • BChange management.
  • CAcommunication plan.
  • DAn issues log.

How the community answered

(30 responses)
  • A
    3% (1)
  • C
    93% (28)
  • D
    3% (1)

Why each option

The project team is confused about roles and tasks, indicating a failure in clearly disseminating information about responsibilities and activities.

AArisk register.

A risk register tracks potential problems that may impact the project, not a lack of clarity on current tasks or roles.

BChange management.

Change management is a process for controlling modifications to project scope, schedule, or resources, not for initial task assignment clarity.

CAcommunication plan.Correct

A communication plan defines who needs what information, when they need it, and how it will be delivered, ensuring clarity regarding roles, responsibilities, and tasks within the project team. This prevents ambiguity by establishing structured information flow.

DAn issues log.

An issues log documents problems that have already occurred and need resolution, rather than proactively preventing confusion about roles.

Concept tested: Project communication planning

Topics

#Communications plan#Team roles and responsibilities#Project communication