Which of the following would be included in the Project Charter?

The correct answer is B. Problem statement. The Project Charter formally authorizes a project and provides the project manager with the authority to apply organizational resources to project activities, typically including high-level information like the problem statement.

Tools and documentation

Question

Which of the following would be included in the Project Charter?

Options

  • ACommunication activities
  • BProblem statement
  • CCost baseline
  • DActivity plan

How the community answered

(37 responses)
  • A
    3% (1)
  • B
    89% (33)
  • C
    5% (2)
  • D
    3% (1)

Why each option

The Project Charter formally authorizes a project and provides the project manager with the authority to apply organizational resources to project activities, typically including high-level information like the problem statement.

ACommunication activities

Communication activities are detailed in the Communications Management Plan, which is a subsidiary plan developed after the charter.

BProblem statementCorrect

A Project Charter includes a high-level description of the project, often starting with the business need or problem statement that the project is intended to address, establishing its purpose. This document provides an overview and context for why the project is being initiated.

CCost baseline

The cost baseline is part of the Cost Management Plan, a detailed plan developed during the planning phase, not a high-level element of the charter.

DActivity plan

An activity plan, or schedule, contains detailed tasks and timelines, which are developed later during the planning process, not in the high-level Project Charter.

Concept tested: Project Charter components