PK0-003 · Question #148

The project sponsor has asked for the project to be delivered two months earlier than originally planned with no changes to the deliverables, cost, or the project team. Which of the following schedule

The correct answer is A. Optimizing. To deliver a project earlier without altering deliverables, cost, or the team, the most appropriate technique involves finding efficiencies and improving execution.

Project management concepts

Question

The project sponsor has asked for the project to be delivered two months earlier than originally planned with no changes to the deliverables, cost, or the project team. Which of the following schedule planning techniques could be used to meet this request?

Options

  • AOptimizing
  • BCrashing
  • CDelaying
  • DResource leveling

How the community answered

(31 responses)
  • A
    77% (24)
  • B
    13% (4)
  • C
    6% (2)
  • D
    3% (1)

Why each option

To deliver a project earlier without altering deliverables, cost, or the team, the most appropriate technique involves finding efficiencies and improving execution.

AOptimizingCorrect

Optimizing the project schedule involves streamlining processes, improving resource utilization, or finding more efficient ways to execute tasks within existing constraints, thereby reducing the project duration without adding cost or changing the team.

BCrashing

Crashing is a schedule compression technique that involves adding resources or working overtime to critical path activities, which inherently increases project costs, violating a key constraint of the request.

CDelaying

Delaying would result in the project finishing later than planned, which is the opposite of the sponsor's request to deliver earlier.

DResource leveling

Resource leveling adjusts the schedule to smooth resource allocation, which often extends the project duration to avoid resource over-allocation, thus not meeting the request for an earlier delivery.

Concept tested: Schedule compression techniques

Topics

#schedule management#schedule compression#project acceleration#optimizing schedule