A project manager is performing activity sequencing with the project team. Each activity is written in a box with arrows linking the boxes according to their dependencies. Which of the following tools

The correct answer is B. Precedence Diagramming Method (PDM). The Precedence Diagramming Method (PDM) is a project scheduling technique where activities are represented as nodes (boxes) and connected by arrows indicating their dependencies.

Tools and documentation

Question

A project manager is performing activity sequencing with the project team. Each activity is written in a box with arrows linking the boxes according to their dependencies. Which of the following tools is the project manager utilizing?

Options

  • AArrow Diagramming Method (ADM)
  • BPrecedence Diagramming Method (PDM)
  • CCritical Path Method (CPM)
  • DCritical Chain Method (CCM)

How the community answered

(20 responses)
  • B
    95% (19)
  • D
    5% (1)

Why each option

The Precedence Diagramming Method (PDM) is a project scheduling technique where activities are represented as nodes (boxes) and connected by arrows indicating their dependencies.

AArrow Diagramming Method (ADM)

The Arrow Diagramming Method (ADM) represents activities as arrows and events as nodes, which contradicts the description of activities being in boxes.

BPrecedence Diagramming Method (PDM)Correct

The Precedence Diagramming Method (PDM), also known as Activity-on-Node (AON), represents project activities as nodes (boxes) and their dependencies as arrows, which directly matches the description of the project manager's tool.

CCritical Path Method (CPM)

The Critical Path Method (CPM) is an algorithm for scheduling project activities to identify the longest sequence and determine minimum project duration, not a diagramming technique itself.

DCritical Chain Method (CCM)

The Critical Chain Method (CCM) is a project management method that focuses on managing buffers to account for resource contention and uncertainty, not a diagramming method for activity sequencing.

Concept tested: Activity sequencing diagramming methods

Source: https://docs.microsoft.com/en-us/project-for-the-web/diagram-predecessor-successor-tasks

Topics

#activity sequencing#PDM#scheduling tools#dependencies

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice