Question
A project manager is performing activity sequencing with the project team. Each activity is written in a box with arrows linking the boxes according to their dependencies. Which of the following tools is the project manager utilizing?
Options
- AArrow Diagramming Method (ADM)
- BPrecedence Diagramming Method (PDM)
- CCritical Path Method (CPM)
- DCritical Chain Method (CCM)