nerdexam
CompTIA

PK0-003 · Question #365

A project's Critical Path is:

The correct answer is B. Asequence of activities that takes the longest time to complete.. The Critical Path Method (CPM) identifies the sequence of project activities that dictates the overall project duration.

Project management concepts

Question

A project's Critical Path is:

Options

  • AAsequence of activities that takes the shortest time to complete.
  • BAsequence of activities that takes the longest time to complete.
  • CAsequence of the activities that can be delayed without impacting the project's end date.
  • DAsequence of the project's activities required to meet the defined milestones.

How the community answered

(34 responses)
  • B
    91% (31)
  • C
    6% (2)
  • D
    3% (1)

Why each option

The Critical Path Method (CPM) identifies the sequence of project activities that dictates the overall project duration.

AAsequence of activities that takes the shortest time to complete.

The critical path represents the longest, not shortest, duration sequence of activities, as it dictates the overall project completion time.

BAsequence of activities that takes the longest time to complete.Correct

The critical path is defined as the sequence of project activities that determines the earliest completion date of the project by having the longest duration, meaning any delay to these activities directly delays the entire project. This path has zero float or slack, indicating no flexibility in its schedule.

CAsequence of the activities that can be delayed without impacting the project's end date.

Activities on the critical path cannot be delayed without impacting the project's end date; instead, activities with 'float' or 'slack' can be delayed.

DAsequence of the project's activities required to meet the defined milestones.

While critical path activities contribute to milestones, the primary definition relates to the overall project duration and identifying the longest sequence, not merely activities for milestones.

Concept tested: Project management - Critical Path Method (CPM)

Topics

#Critical path#Schedule management#Project scheduling

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice