PK0-003 · Question #392
A project manager has failed to obtain the necessary permits from the local building commission. The project has been stopped because of a failure to understand the importance of:
The correct answer is C. standards compliance.. The project stopping due to the failure to obtain necessary permits from the local building commission indicates a failure to understand the importance of standards compliance.
Question
A project manager has failed to obtain the necessary permits from the local building commission. The project has been stopped because of a failure to understand the importance of:
Options
- Ainternal process compliance.
- Brisk avoidance.
- Cstandards compliance.
- Daudit trail compliance.
How the community answered
(19 responses)- A5% (1)
- B5% (1)
- C89% (17)
Why each option
The project stopping due to the failure to obtain necessary permits from the local building commission indicates a failure to understand the importance of standards compliance.
Internal process compliance relates to following an organization's internal procedures, not external regulatory requirements like building permits.
Risk avoidance is a strategy to eliminate a risk, but the question focuses on the reason for the project stoppage, which is the non-compliance with external rules.
Local building commissions enforce building codes, regulations, and other standards that projects must adhere to for legal operation and safety. Failing to obtain the necessary permits demonstrates a lack of understanding or adherence to these required external standards, leading to project stoppage.
Audit trail compliance pertains to maintaining records of actions for auditing purposes, not the initial requirement for obtaining regulatory permits themselves.
Concept tested: Project regulatory and standards compliance