PK0-003 · Question #378
The project manager can use the lowest level of the risk breakdown structure (RBS) to create which of the following documents?
The correct answer is B. Risk checklist. The lowest level of the Risk Breakdown Structure (RBS) provides granular risk categories that are highly useful for constructing a detailed risk checklist.
Question
The project manager can use the lowest level of the risk breakdown structure (RBS) to create which of the following documents?
Options
- ARisk register
- BRisk checklist
- CProbability and impact matrix
- DRisk budget
How the community answered
(32 responses)- A3% (1)
- B94% (30)
- D3% (1)
Why each option
The lowest level of the Risk Breakdown Structure (RBS) provides granular risk categories that are highly useful for constructing a detailed risk checklist.
A risk register is a comprehensive document detailing all identified risks and their attributes, which the RBS contributes to but does not directly create from its lowest level.
The lowest level of the Risk Breakdown Structure (RBS) contains detailed categories of potential risks, which can be directly used as prompts to create a thorough risk checklist. This checklist aids in identifying risks during subsequent projects or phases.
A probability and impact matrix is a tool used for analyzing and prioritizing individual risks, not a document created directly from the lowest level of the RBS.
A risk budget is the financial allocation for potential risks, derived from risk analysis, and is not a document directly created from the RBS's lowest level.
Concept tested: Risk breakdown structure (RBS) utility