PK0-003 · Question #377

Administrative closure of a project includes which of the following activities?

The correct answer is C. Release project team members.. Administrative closure is the formal process of completing a project or phase, which includes the organized disengagement of resources.

Project life cycle phases

Question

Administrative closure of a project includes which of the following activities?

Options

  • AClose all contracts.
  • BCreate performance reports.
  • CRelease project team members.
  • DObtain a formal sign-off from the project team.

How the community answered

(31 responses)
  • A
    3% (1)
  • B
    6% (2)
  • C
    87% (27)
  • D
    3% (1)

Why each option

Administrative closure is the formal process of completing a project or phase, which includes the organized disengagement of resources.

AClose all contracts.

Closing all contracts is part of procurement closure, which is a specialized process related to, but distinct from, administrative project closure.

BCreate performance reports.

Creating performance reports is an ongoing process throughout project execution and monitoring, not exclusive to the final administrative closure phase.

CRelease project team members.Correct

Releasing project team members is a key administrative closure activity, formally disengaging them from the project and allowing them to be assigned to new work. This ensures proper resource management as the project concludes.

DObtain a formal sign-off from the project team.

Obtaining a formal sign-off is typically done by the customer or key stakeholders, not from the internal project team members themselves.

Concept tested: Project administrative closure activities

Topics

#Project closure#Administrative closure#Team release