nerdexam
ExamsPK0-003Questions#389
CompTIA

PK0-003 · Question #389

PK0-003 Question #389: Real Exam Question with Answer & Explanation

The correct answer is D: Risk transference. See the full explanation below for the reasoning.

Question

Several key resources will be unavailable at the end of the project. The key stakeholders want to outsource the project to a third party. Which of the following risk responses is described in this situation?

Options

  • ARisk avoidance
  • BRisk mitigation
  • CRisk acceptance
  • DRisk transference

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice