CompTIA
PK0-003 · Question #389
PK0-003 Question #389: Real Exam Question with Answer & Explanation
The correct answer is D: Risk transference. See the full explanation below for the reasoning.
Question
Several key resources will be unavailable at the end of the project. The key stakeholders want to outsource the project to a third party. Which of the following risk responses is described in this situation?
Options
- ARisk avoidance
- BRisk mitigation
- CRisk acceptance
- DRisk transference
Community Discussion
No community discussion yet for this question.