PK0-003 · Question #335
Which of the following is the project manager implementing when they allocate additional resources to a set of tasks that are in the critical path and are slowing down the project completion?
The correct answer is A. Crashing. The project manager is implementing crashing, a schedule compression technique that involves allocating additional resources to critical path activities to shorten their duration and the overall project completion time.
Question
Which of the following is the project manager implementing when they allocate additional resources to a set of tasks that are in the critical path and are slowing down the project completion?
Options
- ACrashing
- BOptimizing
- CControlling
- DFast tracking
How the community answered
(31 responses)- A87% (27)
- B3% (1)
- D10% (3)
Why each option
The project manager is implementing crashing, a schedule compression technique that involves allocating additional resources to critical path activities to shorten their duration and the overall project completion time.
Crashing is a schedule compression technique where additional resources are assigned to critical path activities to reduce their duration, thereby shortening the overall project schedule, typically at an increased cost.
Optimizing is a broader term for making a process or system as effective as possible, not a specific technique for shortening a project schedule by adding resources.
Controlling is a project management process group that monitors project progress and ensures objectives are met, which is a continuous activity, not a specific technique for accelerating a schedule.
Fast tracking involves performing activities in parallel that would normally be done in sequence to shorten the schedule, rather than adding resources to individual tasks.
Concept tested: Schedule compression techniques - Crashing
Source: https://www.projectmanager.com/blog/crashing-vs-fast-tracking