The correct answer is A: Reviewing holiday and vacation schedule with all team members.. See the full explanation below for the reasoning.

Question

A project manager has a project with staff in four different countries. When generating the resource management plan, which of the following should be considered FIRST?

Options

  • AReviewing holiday and vacation schedule with all team members.
  • BGetting the email address of all the employees.
  • CLocating each employee on the map in the office.
  • DUnderstanding the international country code of all the team members.