Question
A project manager has a project with staff in four different countries. When generating the resource management plan, which of the following should be considered FIRST?
Options
- AReviewing holiday and vacation schedule with all team members.
- BGetting the email address of all the employees.
- CLocating each employee on the map in the office.
- DUnderstanding the international country code of all the team members.