Question
An approved change request has delayed the project start date without modifying the completion date. The project sponsor has requested the project manager to pursue an option with the LOWEST initial cost. Which of the following methods should the project manager consider?
Options
- AParametric estimating
- BRolling wave planning
- CCrashing
- DFast tracking