nerdexam
CompTIA

PK0-003 · Question #307

Click on the exhibit button. Which of the following is the critical path?

The correct answer is D. Start-A-D-end. The critical path is the longest sequence of activities in a project network diagram, which determines the shortest possible duration for the entire project.

Tools and documentation

Question

Click on the exhibit button. Which of the following is the critical path?

Exhibit

PK0-003 question #307 exhibit

Options

  • AStart-A-B-E-F-end
  • BStart-A-B-C-end
  • CStart-A-B-E-C-end
  • DStart-A-D-end

How the community answered

(35 responses)
  • A
    6% (2)
  • B
    17% (6)
  • C
    6% (2)
  • D
    71% (25)

Why each option

The critical path is the longest sequence of activities in a project network diagram, which determines the shortest possible duration for the entire project.

AStart-A-B-E-F-end

This path has a shorter total duration than the critical path, meaning it has some float and can be delayed without impacting the project end date.

BStart-A-B-C-end

This path has a shorter total duration than the critical path, meaning it has some float and can be delayed without impacting the project end date.

CStart-A-B-E-C-end

This path has a shorter total duration than the critical path, meaning it has some float and can be delayed without impacting the project end date.

DStart-A-D-endCorrect

The path Start-A-D-end represents the sequence of activities that, when summed for their individual durations, results in the longest total duration for the project. This means it has zero float and any delay on this path will delay the entire project.

Concept tested: Critical Path Method (CPM) identification

Topics

#Critical path#Schedule analysis#Network diagram

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice