PK0-003 · Question #340
Which of the following should be used when determining the details of a project component or scope entry?
The correct answer is A. WBS Dictionary. This question asks which project document is used to provide detailed information for individual project components or scope entries.
Question
Which of the following should be used when determining the details of a project component or scope entry?
Options
- AWBS Dictionary
- BProject Management Plan
- CWork Breakdown Structure
- DProject Charter
How the community answered
(33 responses)- A91% (30)
- B3% (1)
- D6% (2)
Why each option
This question asks which project document is used to provide detailed information for individual project components or scope entries.
The WBS Dictionary provides detailed information for each component in the Work Breakdown Structure, clarifying the scope of work, deliverables, activities, schedule milestones, and cost estimates associated with each work package or control account.
The Project Management Plan is the overarching document that integrates all subsidiary plans and baselines, but it does not provide the granular, detailed descriptions for individual WBS components itself.
The Work Breakdown Structure (WBS) is a hierarchical decomposition of the project's scope, but it is a structure or list, not a document that contains the detailed narrative description of each entry.
The Project Charter formally authorizes the project, defines high-level objectives and boundaries, and names the project manager, but it does not contain the detailed breakdown of project components.
Concept tested: WBS Dictionary purpose and usage
Topics