nerdexam
CompTIA

PK0-003 · Question #320

The project manager has received an approved change request. Which of the following actions should the project manager take NEXT?

The correct answer is D. Develop a plan to incorporate the change into the project. Upon receiving an approved change request, the project manager's immediate next step is to integrate the change into the project by developing an implementation plan.

Project management concepts

Question

The project manager has received an approved change request. Which of the following actions should the project manager take NEXT?

Options

  • ASchedule a meeting with the change advisory board to discuss the impact of the change
  • BPerform a probability and impact assessment on the approved change
  • CHold a team meeting to ensure the change is immediately implemented
  • DDevelop a plan to incorporate the change into the project

How the community answered

(33 responses)
  • A
    6% (2)
  • B
    3% (1)
  • C
    12% (4)
  • D
    79% (26)

Why each option

Upon receiving an approved change request, the project manager's immediate next step is to integrate the change into the project by developing an implementation plan.

ASchedule a meeting with the change advisory board to discuss the impact of the change

Discussions with the change advisory board and impact analysis typically occur -before- a change request is approved, as part of the evaluation process.

BPerform a probability and impact assessment on the approved change

A probability and impact assessment is part of the initial change request analysis and evaluation, which happens -before- approval, to determine whether the change should be approved.

CHold a team meeting to ensure the change is immediately implemented

Implementing a change immediately without a proper plan can lead to unforeseen issues, risks, and disruption; planning is crucial after approval.

DDevelop a plan to incorporate the change into the projectCorrect

Once a change request is approved, the project manager must proceed with integrating it into the project baseline. This involves developing a detailed plan for how the change will be implemented, including updating project documents, schedules, budgets, and resource assignments, before actual execution begins.

Concept tested: Project change management process

Topics

#Change management#Change implementation#Project planning

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice