PK0-003 Exam Questions
500 real PK0-003 exam questions with expert-verified answers and explanations. Page 1 of 10.
- Question #1Tools and documentation
Which of the following are components of a project charter? (Select THREE).
project charterproject documentationproject objectivesstakeholder identification - Question #2Tools and documentation
Which of the following would be included in a project scope document? (Select THREE).
project scopescope documentationproject constraintsKPIs - Question #3Tools and documentation
Which of the following are common components of a project transition plan? (Select TWO).
transition planproject closeoutownership identification - Question #4Tools and documentation
The communication plan states the weekly project status updates will be distributed via email. Which of the following components of a communication plan is missing?
communication planproject communicationdistribution list - Question #5Project management concepts
Which of the following personnel should sign the project charter?
project charterproject authorizationstakeholders - Question #6Tools and documentation
Which of the following would be included in the project charter? (Select TWO).
project charterproject descriptionbusiness case - Question #7Project management concepts
An ongoing project that is currently on schedule has had the required completion date moved up by one week; however, the project scope remains the same. Which of the following woul...
triple constraintschedule managementcost managementproject impact - Question #8Project management concepts
Which of the following describes crashing a project schedule?
schedule crashingschedule compressionproject resources - Question #9Project life cycle phases
Which of the following activities occur during a project kick-off meeting? (Select TWO).
kick-off meetingproject initiationproject objectivesteam roles - Question #10Tools and documentation
A project manager is performing activity sequencing with the project team. Each activity is written in a box with arrows linking the boxes according to their dependencies. Which of...
activity sequencingPDMscheduling toolsdependencies - Question #11Tools and documentation
A project manager is recording the probability and impact of an uncertain event. Which of the following would be the BEST document to capture this data?
risk managementrisk registerprobability and impact - Question #12Project management concepts
During the weekly status meeting, it is determined the project will take two months longer to complete. The customer asks the project manager to modify the original end date to the...
change managementchange requestproject scheduleproject control - Question #13Tools and documentation
A project manager is reviewing the ownership, date, and the necessary training for a deliverable. Which of the following documents would include this information?
transition plandeliverable handoverproject closeout - Question #14Project life cycle phases
Which of the following activities would happen LAST in procurement management?
procurement managementcontract administrationproject closeout - Question #15Tools and documentation
Which of the following tools is used to determine the prevalent issues related to quality?
quality managementPareto chartquality toolsissue identification - Question #16Project management concepts
A project was originally budgeted for $500,000. So far, the EV and AC on the project are equal. Two approved change requests have been submitted since the project began. One necess...
earned value managementBACcost managementchange control - Question #17Project management concepts
A project manager is managing a project that is scheduled to take ten months to complete. The project is in its sixth month and $450,000 has been spent. The project budget is $990,...
earned value managementplanned valueEVM metrics - Question #18Tools and documentation
A project sponsor is adamant that a complex project must be completed within 12 months. Based on lessons learned from previous projects of this type, the project manager believes t...
Monte Carlo analysisquantitative risk analysisschedule riskproject simulation - Question #19Basics of IT and governance
Which of the following are main aspects of organizational governance? (Select TWO).
organizational governancedecision oversightstandards compliance - Question #20Project management concepts
Using the work breakdown structure (WBS) and knowledge of team member availability, the project manager is able to:
WBSresource assignmenttask schedulingresource availability - Question #21Project management concepts
A project manager needs to assign team members to begin project work. Which of the following items must the project manager have before assignments can be made? (Select TWO).
Resource allocationWork Breakdown Structure (WBS)Project planning - Question #22Project life cycle phases
Which of the following is the FINAL step in pre-project setup?
Project initiationProject approvalProject charter - Question #23Tools and documentation
The project charter details which of the following?
Project charterProject deliverablesScope definition - Question #24Project management concepts
There are three teams assigned to the same project. Two of the project teams are ahead of schedule; however, the product does not meet the needed quality standards. The third proje...
Quality managementSchedule managementTeam communicationProblem-solving - Question #25Tools and documentation
A project manager has to complete an asset inventory project for a large corporation. Several departments have refused to allow access to the equipment to complete the project. The...
Issues managementIssues logStakeholder management - Question #26Project management concepts
A project team is deciding on whether to "make or buy". As part of the decision-making process, the team decides to request a product update from key product suppliers. Which of th...
Procurement managementRFI (Request for Information)Make-or-buy analysis - Question #27Project management concepts
Which of the following is typically the LAST step when acquiring a product or service from a vendor?
Procurement processContract signingVendor management - Question #28Project life cycle phases
A project is nearing completion. Which of the following tasks is required to ensure continuity after the project closes?
Project closureTransition planningOperational handover - Question #29Project management concepts
Two project resources have been involved in several heated arguments based on approaches to meet project requirements. The first resource is convinced that the requirement is inval...
Conflict resolutionTeam managementNegotiationSmoothing - Question #30Project management concepts
Within a corporation, project managers are assigned people based on defined roles and responsibilities. Project resources are temporarily provided to the project but still report t...
Organizational structuresMatrix managementFunctional management - Question #31Project life cycle phases
The project manager is trying to determine what to present at a project kick-off meeting. Should a high-level project schedule be included?
Kick-off meetingProject scheduleStakeholder communication - Question #32Basics of IT and governance
Senior executives within a company have noticed an increasing number of projects failing to deliver to requirements. Which of the following project governance methods will help to...
Project governancePhase gatesProject controlQuality assurance - Question #33Project management concepts
A key supplier has informed the project manager that there will be a two month delay to fulfill an order. Which component of the project plan is affected and which of the following...
Schedule managementRisk managementIssues logSupplier management - Question #34Project management concepts
A specific deliverable is needed in order to meet a project requirement. Another project has already constructed this deliverable and there is a strategic push for re-usable, lever...
Resource reuseCost savingsDependency managementProject optimization - Question #35Project management concepts
Due to unforeseen schedule blowouts, the project manager is forced to compress the next set of activities in order to avoid affecting the project delivery date. Which of the follow...
Schedule compressionFast trackingCrashingSchedule management - Question #36Project management concepts
Which of the following tasks is essential to update a critical production component prior to project delivery?
Change managementChange control processProduction update - Question #37Tools and documentation
Which of the following techniques is premised by a relatively small number of causes resulting in the majority of defects?
Quality managementPareto analysisProblem-solving techniques - Question #38Project management concepts
The project manager has noticed that meeting attendance rates are declining. Regular attendees prefer to talk about the past or upcoming weekend as opposed to reporting on project...
Meeting managementCommunication skillsTeam engagementGround rules - Question #39Project management concepts
The project team is geographically split between two time zones. Which of the following should be performed by the project manager?
Virtual teamsTeam managementCommunication planningTime zone management - Question #40Basics of IT and governance
Due to external market conditions, the Chief Executive Officer (CEO) has announced a company shift in strategic priorities. As such, more focus will be spent on tuning current oper...
Project terminationStrategic alignmentPortfolio managementProject cancellation - Question #41Tools and documentation
Which of the following is included in the project charter?
Project charterProject initiationProject scope - Question #42Project management concepts
Which of the following BEST describes a functional organization?
Organizational structuresFunctional organizationProject context - Question #43Tools and documentation
Which of the following describes the work package level of a WBS?
Work Breakdown StructureWBSWork packageScope definition - Question #44Project management concepts
A project stakeholder wants to make changes to a project after work on the project has already started. Which of the following should the project manager do FIRST?
Change managementChange request processProject control - Question #45Tools and documentation
The difference between a risk matrix and a risk register is that:
Risk managementRisk registerRisk matrix - Question #46Tools and documentation
A project team is writing a new customized point of sale software. The software needs to calculate sales tax 100% of the time on all taxable items of a receipt. This requirement sh...
Quality managementQuality metricsRequirements documentation - Question #47Tools and documentation
A chart of accounts is included in which of the following plans?
Cost managementChart of accountsCost management plan - Question #48Project management concepts
Which of the following are lose-lose conflict resolution techniques?
Conflict resolutionTeam managementCompromise - Question #49Basics of IT and governance
Which of the following regarding project documentation can be found in organizational governance documents? (Select TWO).
Organizational governanceProject documentationDocument control - Question #50Project management concepts
A company is replacing their file server with a new one. During the data migration, the old file server experiences critical hardware failure. The data migration cannot continue un...
Issue managementProblem solvingProject execution