nerdexam
CompTIA

PK0-003 · Question #34

A specific deliverable is needed in order to meet a project requirement. Another project has already constructed this deliverable and there is a strategic push for re-usable, leveraged components to b

The correct answer is C. Plan to leverage the other project's deliverables, make a direct project cost savings and meet. Given a strategic push for reuse and the availability of a needed deliverable from another project, the project manager should leverage it to achieve cost savings and meet requirements efficiently.

Project management concepts

Question

A specific deliverable is needed in order to meet a project requirement. Another project has already constructed this deliverable and there is a strategic push for re-usable, leveraged components to be utilized. Which of the following actions should the project manager take?

Options

  • AIgnore the other project so as not to introduce inter-dependencies between projects as this could
  • BIdentify project dependency as a threat, update risk register and inform stakeholders so that a
  • CPlan to leverage the other project's deliverables, make a direct project cost savings and meet
  • DEscalate the issue to the project sponsor so that a project decision can be made so that the

How the community answered

(52 responses)
  • A
    8% (4)
  • B
    15% (8)
  • C
    54% (28)
  • D
    23% (12)

Why each option

Given a strategic push for reuse and the availability of a needed deliverable from another project, the project manager should leverage it to achieve cost savings and meet requirements efficiently.

AIgnore the other project so as not to introduce inter-dependencies between projects as this could

Ignoring existing, reusable deliverables contradicts the strategic push for leveraging components and is an inefficient approach to project management.

BIdentify project dependency as a threat, update risk register and inform stakeholders so that a

While dependencies exist, in this context, leveraging a pre-existing deliverable is an opportunity for efficiency, not primarily a threat to be managed as a risk.

CPlan to leverage the other project's deliverables, make a direct project cost savings and meetCorrect

Leveraging an existing deliverable from another project directly supports the strategic goal of re-usability, leading to potential project cost savings and ensuring the project requirement is met efficiently.

DEscalate the issue to the project sponsor so that a project decision can be made so that the

Escalation is usually for problems or decisions beyond the PM's authority; leveraging a deliverable, especially with a strategic push for reuse, is a standard PM decision.

Concept tested: Project resource optimization and reuse

Source: https://www.pmi.org/learning/library/project-management-resource-sharing-6007

Topics

#Resource reuse#Cost savings#Dependency management#Project optimization

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice