nerdexam
CompTIA

PK0-003 · Question #35

Due to unforeseen schedule blowouts, the project manager is forced to compress the next set of activities in order to avoid affecting the project delivery date. Which of the following techniques can b

The correct answer is A. Fast tracking B. Crashing. To compress the project schedule and avoid delays, project managers can use fast tracking, which involves performing activities in parallel, or crashing, which means adding resources to shorten activity durations.

Project management concepts

Question

Due to unforeseen schedule blowouts, the project manager is forced to compress the next set of activities in order to avoid affecting the project delivery date. Which of the following techniques can be used to help achieve this? (Select TWO).

Options

  • AFast tracking
  • BCrashing
  • CDelaying
  • DQuality control
  • EScope reduction

How the community answered

(46 responses)
  • A
    87% (40)
  • C
    7% (3)
  • D
    4% (2)
  • E
    2% (1)

Why each option

To compress the project schedule and avoid delays, project managers can use fast tracking, which involves performing activities in parallel, or crashing, which means adding resources to shorten activity durations.

AFast trackingCorrect

Fast tracking is a schedule compression technique where activities that would normally be done in sequence are performed in parallel, overlapping them to shorten the overall project duration.

BCrashingCorrect

Crashing is a schedule compression technique that involves adding or applying more resources (e.g., more staff, overtime, better equipment) to critical path activities to complete them faster, usually at an increased cost.

CDelaying

Delaying activities would extend the project schedule, which is the opposite of the objective to compress activities to avoid affecting the delivery date.

DQuality control

Quality control focuses on monitoring specific project results to determine if they comply with relevant quality standards; it does not directly compress the schedule.

EScope reduction

Scope reduction involves decreasing the amount of work, which is a scope change, not a direct schedule compression technique applied to existing activities.

Concept tested: Project schedule compression techniques

Source: https://www.pmi.org/learning/library/project-schedule-compression-techniques-6288

Topics

#Schedule compression#Fast tracking#Crashing#Schedule management

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice