PK0-003 · Question #36
Which of the following tasks is essential to update a critical production component prior to project delivery?
The correct answer is D. Initiate change control process. To update a critical production component prior to project delivery, it is essential to initiate the change control process to ensure proper evaluation, approval, and management of the modification.
Question
Which of the following tasks is essential to update a critical production component prior to project delivery?
Options
- APerform post-change testing
- BRelease project costs
- CReceive vendor sign-off
- DInitiate change control process
How the community answered
(26 responses)- A4% (1)
- B4% (1)
- C12% (3)
- D81% (21)
Why each option
To update a critical production component prior to project delivery, it is essential to initiate the change control process to ensure proper evaluation, approval, and management of the modification.
Performing post-change testing happens after the change has been implemented, not prior to the project delivery as the initial essential task for updating the component.
Releasing project costs is part of financial management and project closure, not an essential task for initiating an update to a critical production component.
Receiving vendor sign-off may be part of the change implementation or procurement process, but it is not the initial or essential step for updating a component and managing the change itself.
Updating a critical production component is a significant modification that requires initiating the change control process to formally evaluate, approve, schedule, and track the change, ensuring it aligns with project goals and minimizes risks.
Concept tested: Change control process initiation
Source: https://www.pmi.org/learning/library/integrated-change-control-project-management-6523
Topics