PK0-003 · Question #6
Which of the following would be included in the project charter? (Select TWO).
The correct answer is A. Project description E. High level business case. The project charter defines a project's high-level purpose and key components, including its description and an overview of its business justification.
Question
Which of the following would be included in the project charter? (Select TWO).
Options
- AProject description
- BRisk management plan
- CChange management plan
- DStatement of Work (SOW)
- EHigh level business case
How the community answered
(47 responses)- A87% (41)
- B4% (2)
- C6% (3)
- D2% (1)
Why each option
The project charter defines a project's high-level purpose and key components, including its description and an overview of its business justification.
The project description provides a high-level overview of what the project entails, its objectives, and what it aims to achieve, which is fundamental to the project charter.
A detailed risk management plan is developed later in the planning process, not as a high-level component within the project charter.
A change management plan is a subsidiary plan created during the planning phase, providing detailed procedures for managing changes, not a high-level element of the charter.
A Statement of Work (SOW) details the specific work to be performed, deliverables, and timelines for a specific part of the project or for an external vendor, which is more detailed than what is in the charter itself.
A high-level business case or project justification is included in the project charter to explain the reason for the project, its value to the organization, and how it aligns with strategic goals.
Concept tested: Contents of a project charter
Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/project-charter