nerdexam
CompTIA

PK0-003 · Question #7

An ongoing project that is currently on schedule has had the required completion date moved up by one week; however, the project scope remains the same. Which of the following would be the effect on t

The correct answer is D. Cost will increase and time will decrease.. Expediting a project by reducing its completion time while maintaining scope typically leads to increased costs.

Project management concepts

Question

An ongoing project that is currently on schedule has had the required completion date moved up by one week; however, the project scope remains the same. Which of the following would be the effect on the project?

Options

  • ACost will decrease and time will increase.
  • BCost will decrease and time will decrease.
  • CCost will increase and time will increase.
  • DCost will increase and time will decrease.

How the community answered

(46 responses)
  • A
    2% (1)
  • B
    4% (2)
  • C
    2% (1)
  • D
    91% (42)

Why each option

Expediting a project by reducing its completion time while maintaining scope typically leads to increased costs.

ACost will decrease and time will increase.

Decreasing time almost always increases cost in project management scenarios where scope is fixed, not decreases it.

BCost will decrease and time will decrease.

Reducing project time while keeping scope constant will generally increase costs, not decrease them.

CCost will increase and time will increase.

While cost will increase, time will decrease because the completion date was moved up, making this choice incorrect.

DCost will increase and time will decrease.Correct

When the project completion date is moved up (time decreases) while the scope remains the same, additional resources, overtime, or other cost-intensive measures are often required to accelerate activities, thereby increasing the overall project cost. This illustrates the inverse relationship between time and cost when scope is fixed and time is reduced.

Concept tested: Project triple constraint - time, cost, scope relationship

Source: https://www.pmi.org/pmbok-guide-standards/foundational/pmbok/triple-constraint

Topics

#triple constraint#schedule management#cost management#project impact

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice