Which of the following is included in the project charter?

The correct answer is B. Problem statement. The project charter is a formal document that authorizes a project and provides the project manager with the authority to apply organizational resources to project activities. It typically includes the project's purpose and justification, which often stems from a problem statemen

Tools and documentation

Question

Which of the following is included in the project charter?

Options

  • AWork assignments
  • BProblem statement
  • CCost-benefit analysis
  • DFeasibility assessments

How the community answered

(28 responses)
  • A
    4% (1)
  • B
    93% (26)
  • D
    4% (1)

Why each option

The project charter is a formal document that authorizes a project and provides the project manager with the authority to apply organizational resources to project activities. It typically includes the project's purpose and justification, which often stems from a problem statement.

AWork assignments

Work assignments are detailed in later planning documents, such as the WBS and resource assignments, not typically in the high-level project charter.

BProblem statementCorrect

A project charter outlines the project's purpose and objectives, often starting with a problem or business need that the project aims to address. The problem statement defines the core issue the project intends to resolve, providing the project's rationale.

CCost-benefit analysis

A cost-benefit analysis is usually conducted before the charter to justify the project, or as part of more detailed business case analysis, not a primary component within the charter itself.

DFeasibility assessments

Feasibility assessments are typically performed before the project charter is approved to determine if the project is viable, rather than being a direct component of the charter.

Concept tested: Project charter components

Topics

#Project charter#Project initiation#Project scope