PK0-003 · Question #3
Which of the following are common components of a project transition plan? (Select TWO).
The correct answer is A. Extended support C. Ownership identification. A project transition plan outlines the process of handing over project deliverables to the operational team, ensuring smooth integration and ongoing viability.
Question
Which of the following are common components of a project transition plan? (Select TWO).
Options
- AExtended support
- BWork performance
- COwnership identification
- DRisk assessment
- EBudget analysis
How the community answered
(28 responses)- A86% (24)
- B4% (1)
- D7% (2)
- E4% (1)
Why each option
A project transition plan outlines the process of handing over project deliverables to the operational team, ensuring smooth integration and ongoing viability.
Extended support details the level and duration of assistance the project team or designated groups will provide after the solution is deployed.
Work performance information refers to data collected during project execution, used for monitoring, not a component of a transition plan.
Ownership identification clearly designates which individual or team will be responsible for the ongoing maintenance, operation, and future development of the project's outcome.
Risk assessment is an ongoing process throughout the project lifecycle, addressing potential issues, but it is not a direct component of the transition plan itself.
Budget analysis is part of project cost management and financial control, distinct from the steps required for transitioning a project to operations.
Concept tested: Project transition plan components