CompTIA
PK0-003 · Question #16
PK0-003 Question #16: Real Exam Question with Answer & Explanation
Sign in or unlock PK0-003 to reveal the answer and full explanation for question #16. The question stem and answer options stay visible for context.
Question
A project was originally budgeted for $500,000. So far, the EV and AC on the project are equal. Two approved change requests have been submitted since the project began. One necessitated a change in the project that would increase costs by $50,000. The second change request increased costs by $270,000. Which of the following is the new BAC for the project?
Options
- A$500,000
- B$550,000
- C$820,000
- D$920,000
Unlock PK0-003 to see the answer
You've previewed enough free PK0-003 questions. Unlock PK0-003 for full answers, explanations, the timed quiz mode, progress tracking, and the master PDF. Question stem and options stay visible so you can still see what's on the exam.