nerdexam
CompTIA

PK0-003 · Question #18

A project sponsor is adamant that a complex project must be completed within 12 months. Based on lessons learned from previous projects of this type, the project manager believes that the project cann

The correct answer is C. Monte Carlo analysis. To demonstrate the improbability of a proposed project timeline given uncertainties, the project manager can use Monte Carlo analysis.

Tools and documentation

Question

A project sponsor is adamant that a complex project must be completed within 12 months. Based on lessons learned from previous projects of this type, the project manager believes that the project cannot possibly finish in less than 24 months. Which of the following tools can the project manager use to show the improbability of the proposed timeline?

Options

  • APareto Diagram
  • BDecision tree
  • CMonte Carlo analysis
  • DQuantitative risk analysis

How the community answered

(21 responses)
  • A
    24% (5)
  • B
    5% (1)
  • C
    62% (13)
  • D
    10% (2)

Why each option

To demonstrate the improbability of a proposed project timeline given uncertainties, the project manager can use Monte Carlo analysis.

APareto Diagram

A Pareto Diagram is a bar chart showing the frequency of causes for problems, ordered from most to least frequent, used for identifying the most significant problems.

BDecision tree

A Decision tree is a diagram that models possible decision paths and their outcomes, used for making choices under uncertainty, not for simulating project completion times.

CMonte Carlo analysisCorrect

Monte Carlo analysis is a simulation technique that performs a large number of iterations to calculate a range of possible outcomes and their probabilities. This makes it ideal for showing the likelihood of completing a project by a specific date, considering the variability in task durations and other project uncertainties.

DQuantitative risk analysis

Quantitative risk analysis is a process that numerically analyzes the effect of identified risks on overall project objectives, and while Monte Carlo is a tool used within this process, it is not the process itself.

Concept tested: Project risk analysis - Monte Carlo simulation

Source: https://www.projectmanager.com/blog/monte-carlo-simulation

Topics

#Monte Carlo analysis#quantitative risk analysis#schedule risk#project simulation

Community Discussion

No community discussion yet for this question.

Full PK0-003 Practice