PK0-003 · Question #13
A project manager is reviewing the ownership, date, and the necessary training for a deliverable. Which of the following documents would include this information?
The correct answer is A. Transition plan. A transition plan is the appropriate document for reviewing deliverable ownership, transition dates, and required training as it details the handover of project outputs into operational use.
Question
A project manager is reviewing the ownership, date, and the necessary training for a deliverable. Which of the following documents would include this information?
Options
- ATransition plan
- BQuality plan
- CChange Control plan
- DProcurement plan
How the community answered
(22 responses)- A91% (20)
- B5% (1)
- D5% (1)
Why each option
A transition plan is the appropriate document for reviewing deliverable ownership, transition dates, and required training as it details the handover of project outputs into operational use.
The transition plan specifically addresses how deliverables will be handed over to the receiving organization, detailing elements such as ownership, the timing of the transition, and any necessary training for the users or support staff. This ensures a smooth integration of the project's output into ongoing operations.
A quality plan focuses on how quality requirements will be met and managed throughout the project, not the post-project handover details.
A change control plan outlines the process for managing changes to project baselines, not the operational transition of deliverables.
A procurement plan details how external products, services, or results will be acquired, not the internal transfer of project deliverables.
Concept tested: Project deliverable transition planning
Source: https://www.pmi.org/disciplined-agile/resources/project-transition-plan