- Question #351Resource Management
Project team members begin to address the project work and technical decisions. The project team is in which of the following stages of team development?
team developmentTuckman stagesstormingproject team - Question #352Resource Management
Placing many or all of the most active project team members in the same physical location to enhance their ability to perform as a team is called which of the following?
co-locationteam managementphysical locationteam performance - Question #353Resource Management
Emphasizing areas of agreement rather than areas of difference is part which of the following conflict management techniques?
smoothingconflict managementconflict resolutionteam management - Question #354Communication Management
Which knowledge area is concerned with the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of...
Communications Managementproject informationknowledge areasinformation disposition - Question #355Communication Management
Which of the following involves making information available to project stakeholders in a timely ISEB ISEB-PM1 Exam manner?
information distributionstakeholder communicationtimely informationcommunications management - Question #356Communication Management
Forecasts, requested changes, recommended corrective actions, and organizational process asset updates are all outputs of which process?
performance reportingforecastscorrective actionsprocess outputs - Question #357Communication Management
Which of the following is contained within the communications management plan?
communications management planglossaryplanning outputsproject documentation - Question #358Communication Management
Which knowledge area employs the processes required to ensure timely and appropriate generation, collection, distribution, storage, retrieval, and ultimate disposition of project i...
knowledge areasproject communications managementinformation managementprocess groups - Question #359Communication Management
Approved change requests, approved corrective actions, and updates to organizational process assets are all outputs of which project management process?
manage stakeholdersprocess outputschange requestsorganizational process assets - Question #360Communication Management
What is a technique used in the performance reporting process?
performance reportingstatus review meetingscommunication techniquestools and techniques - Question #361Communication Management
What is the number of stakeholders, if the project has 28 potential communication channels?
communication channels formulastakeholder calculationn(n-1)/2quantitative analysis - Question #362Communication Management
What information does the stakeholder register contain?
stakeholder registeridentification informationstakeholder documentationplanning outputs - Question #363Communication Management
Stakeholder analysis identifies what information and relates it to the purpose of the project?
stakeholder analysisstakeholder interestsstakeholder expectationsstakeholder influence - Question #364Communication Management
Which of the following is a tool and technique to the Manage Stakeholder Expectations process?
manage stakeholder expectationsinterpersonal skillstools and techniquesstakeholder engagement - Question #365Risk Management
When using the Delphi technique for gathering information, what forecasting method is being used?
Delphi techniquejudgmental forecastinginformation gatheringexpert elicitation - Question #366Communication Management
Which of the following is one of the key components of the basic communications model?
communications modelencode decodesender receivercommunication theory - Question #367Communication Management
Which of the following is a tool or technique for distribute information?
distribute informationcommunication methodstools and techniquesinformation distribution - Question #368Project Control
A project manager convenes a meeting to determine why the time to produce one product according to specifications has increased from one day to three days over the past month. Whic...
variance analysisperformance measurementquality controlschedule variance - Question #369Communication Management
There are seven members on the project team not counting the project manager and the sponsor. How many communication channels are there?
communication channels formulan(n-1)/2team size calculationstakeholder count - Question #370Communication Management
ABC project is at risk for failing to achieve a major project objective due to unresolved stakeholder issues. Team member morale is low. Who is primarily responsible for the projec...
stakeholder managementproject manager responsibilitymanage stakeholder expectationsaccountability - Question #371Communication Management
When communicating with large audiences, which communication method works most effectively?
pull communicationlarge audiencecommunication methodsinformation distribution - Question #372Risk Management
What are assigned risk ratings based upon?
risk ratingsprobability and impactrisk assessmentrisk scoring - Question #373Risk Management
Which of the following processes includes prioritizing risks for subsequent further analysis or action by assessing and combining their probability of occurrence and impact?
qualitative risk analysisrisk prioritizationprobabilityimpact assessment - Question #374Risk Management
Which of the following documents allows the project manager to assess risks that may require near term action?
risk urgency assessmentnear-term risk actionrisk monitoringrisk documentation - Question #375Risk Management
Which of the following is an example of a technique used in quantitative risk analysis?
quantitative risk analysissensitivity analysisrisk techniquesnumerical analysis - Question #376Risk Management
When does risk monitoring and control occur?
risk monitoring and controlproject lifecyclecontinuous monitoringtiming - Question #377Risk Management
A risk may be graded into different priorities by which process?
qualitative risk analysisrisk prioritizationrisk gradingrisk processes - Question #378Risk Management
ISEB ISEB-PM1 Exam Quality and credibility of the qualitative risk analysis process requires that different levels of the risk's probabilities and impacts be defined is the definit...
qualitative risk analysisrisk probabilityrisk impactrisk definitions - Question #379Risk Management
What is one of the objectives of project risk management?
risk management objectivespositive risksopportunitiesrisk strategy - Question #380Risk Management
Which of the following risk response strategies involves allocating ownership of a positive risk to a third party?
risk response strategiespositive riskshare strategyopportunity management - Question #381Risk Management
Taking out insurance in relation to risk management is called what?
risk transferenceinsurancerisk response strategies - Question #382Risk Management
What risk technique is used to quantify the probability and impact of risks on project objectives?
quantitative risk analysisinterviewing techniquerisk quantificationprobability impact - Question #383Project Planning
What defines the portion of work included in a contract for items being purchased or acquired?
contract SOWstatement of workscope definitionprocurement - Question #384Resource Management
Which of the following is an example of the simplest fixed-price contract?
fixed-price contractpurchase ordercontract typesprocurement - Question #385Resource Management
Which of the following lists contain processes that are included within Project Procurement Management?
procurement processesplan procurementsseller responsesselect sellers - Question #386Project Planning
Which type of analysis is used as a general management technique within the Plan Procurements Process?
make or buy analysisplan procurementsprocurement planninggeneral management techniques - Question #387Resource Management
A purchase order for a specified item to be delivered by a specified date for a specified price is the simplest form of what type of contract? ISEB ISEB-PM1 Exam
fixed-price contractlump-sum contractcontract typespurchase order - Question #388Resource Management
What is the tool and technique used to request seller responses?
bidder conferencesseller responsesprocurement toolsrequest seller responses - Question #389Project Control
A contract change control system defines which of the following?
contract change controlprocurement modificationchange control systemcontract administration - Question #390Resource Management
In what type of contract is the seller reimbursed for all allowable costs for performing the contract work and receives a predetermined fee based upon achieving certain performance...
cost-plus-incentive-feeCPIFcontract typesperformance objectives - Question #391Organizational Aspects of Project Management
Who decides buyer and seller roles in a teaming agreement?
teaming agreementprocurementbuyer-seller rolesexecutive management - Question #392Resource Management
In which of the following contract types is a price ceiling set and any additional costs above the price ceiling becomes the responsibility of the performing organization?
fixed-price-incentive-feeFPIFprice ceilingcontract types - Question #393Risk Management
The degree of risk shared between the buyer and seller is determined by the:
contract typesrisk sharingbuyer seller riskprocurement risk - Question #394Resource Management
Company A bought a well-defined project deliverable from Company B. Company A will pay a fixed total price plus a percentage premium for the schedule target achieved. For which typ...
FPIFfixed-price-incentive-feeschedule incentivecontract types - Question #395Project Control
Negotiated Settlements are an example of a technique used in which Project Procurement Management Process?
negotiated settlementsclose procurementscontract closeoutprocurement closure - Question #396Project Control
Which project management process ensures the seller's performance meets procurement requirements and that the buyer performs according to the terms of the legal contract? ISEB ISEB...
administer procurementscontract complianceprocurement performanceseller performance - Question #397Resource Management
Which contract type is typically used whenever the seller's performance period spans a considerable period of years?
FP-EPAeconomic price adjustmentlong-term contractscontract types - Question #398The Project Management Lifecycle
The project management information system is used as tools and techniques in which of the following processes?
PMISproject management information systemdirect and manage executionproject execution - Question #399The Project Management Lifecycle
Final product transition is an output of which process?
project closurefinal product transitionprocess outputsClose Project or Phase - Question #400Project Control
Which of the following provides a standardized, effective, and efficient way to centrally manage approved changes and baselines within a project?
configuration managementchange controlbaselineschange management system