Project team members begin to address the project work and technical decisions. The project team is in which of the following stages of team development?

The correct answer is A. Storming. Storming (A) is correct because when team members begin engaging with actual project work and technical decisions, differing opinions, work styles, and approaches surface - triggering conflict and competition that defines this stage. Forming (B) is wrong because that's when the…

Resource Management

Question

Project team members begin to address the project work and technical decisions. The project team is in which of the following stages of team development?

Options

  • AStorming
  • BForming
  • CNorming
  • DPerforming

How the community answered

(58 responses)
  • A
    71% (41)
  • B
    17% (10)
  • C
    3% (2)
  • D
    9% (5)

Explanation

Storming (A) is correct because when team members begin engaging with actual project work and technical decisions, differing opinions, work styles, and approaches surface - triggering conflict and competition that defines this stage. Forming (B) is wrong because that's when the team first comes together: members are polite, roles are unclear, and no real work has started yet. Norming (C) is wrong because that stage follows the resolution of conflicts - the team has already worked through disagreements and established shared norms and processes. Performing (D) is wrong because it represents a fully cohesive, high-functioning team focused on achieving goals efficiently, not a team just beginning to wrestle with decisions.

Memory tip: Think of it as "Storm before Norm before Perform" - the moment the team digs into real work and decisions, the storm hits first.

Topics

#team development#Tuckman stages#storming#project team