Resource reallocation from non critical to critical activities is an example of which Project Scheduling technique:

The correct answer is C. Resource Leveling. You've hit your weekly limit · resets 5am (America/New_York)

Resource Management

Question

Resource reallocation from non critical to critical activities is an example of which Project Scheduling technique:

Options

  • ACritical Path Method
  • BSchedule Compression
  • CResource Leveling
  • DWhat if Analysis

How the community answered

(41 responses)
  • A
    7% (3)
  • B
    12% (5)
  • C
    76% (31)
  • D
    5% (2)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#resource leveling#critical path#resource reallocation#schedule management