Resource reallocation from non critical to critical activities is an example of which Project Scheduling technique:
The correct answer is C. Resource Leveling. You've hit your weekly limit · resets 5am (America/New_York)
Resource Management
Question
Resource reallocation from non critical to critical activities is an example of which Project Scheduling technique:
Options
- ACritical Path Method
- BSchedule Compression
- CResource Leveling
- DWhat if Analysis
How the community answered
(41 responses)- A7% (3)
- B12% (5)
- C76% (31)
- D5% (2)
Explanation
You've hit your weekly limit · resets 5am (America/New_York)
Topics
#resource leveling#critical path#resource reallocation#schedule management