Smoothing out resource requirements from period to period is called resource _____.
The correct answer is B. Leveling. You've hit your weekly limit · resets 5am (America/New_York)
Resource Management
Question
Smoothing out resource requirements from period to period is called resource _____.
Options
- ANone of the other alternatives apply.
- BLeveling.
- CQuantification
- DPartitioning
- EAllocation.
How the community answered
(62 responses)- A5% (3)
- B77% (48)
- C2% (1)
- D13% (8)
- E3% (2)
Explanation