Smoothing out resource requirements from period to period is called resource _____.

The correct answer is B. Leveling. You've hit your weekly limit · resets 5am (America/New_York)

Resource Management

Question

Smoothing out resource requirements from period to period is called resource _____.

Options

  • ANone of the other alternatives apply.
  • BLeveling.
  • CQuantification
  • DPartitioning
  • EAllocation.

How the community answered

(62 responses)
  • A
    5% (3)
  • B
    77% (48)
  • C
    2% (1)
  • D
    13% (8)
  • E
    3% (2)

Explanation

You've hit your weekly limit · resets 5am (America/New_York)

Topics

#resource leveling#resource scheduling#capacity smoothing