ISEB-PM1 · Question #548
You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedy films for the big screen. Your latest project has just been completed and accepted. You've been…
The correct answer is B. This project ended due to extinction because it was completed and accepted. ISEB ISEB-PM1 Exam
The Project Management Lifecycle
Question
You are a project manager for Cinema Snicker Productions. Your company specializes in producing comedy films for the big screen. Your latest project has just been completed and accepted. You've been given your next project, which starts right away. Which of the following statements is true?
Options
- AThis project ended due to integration because it was completed and accepted.
- BThis project ended due to extinction because it was completed and accepted.
- CThis project ended due to integration because it was completed and accepted and the project
- DThis project ended due to addition because it was completed and accepted and archived into
How the community answered
(54 responses)- A15% (8)
- B72% (39)
- C9% (5)
- D4% (2)
Explanation
ISEB ISEB-PM1 Exam
Topics
#project closure#extinction#project completion#project termination