The project charter is developed by:
The correct answer is B. senior management and the project manager. You've hit your session limit · resets 10:20pm (America/New_York)
The Project Management Lifecycle
Question
The project charter is developed by:
Options
- Athe customer
- Bsenior management and the project manager
- Csenior management
- DNone of the other alternatives apply.
- Ethe project manager
How the community answered
(51 responses)- B84% (43)
- C4% (2)
- D10% (5)
- E2% (1)
Explanation
You've hit your session limit · resets 10:20pm (America/New_York)
Topics
#project charter#project initiation#senior management#project authorization