The purpose of configuration management is to:

The correct answer is B. control change throughout the project. You've hit your session limit · resets 10:20pm (America/New_York)

Project Control

Question

The purpose of configuration management is to:

Options

  • Acontrol change during the production only
  • Bcontrol change throughout the project
  • Cinform the project manager of changes
  • Dgenerate engineering change proposals
  • Einsure drawings are updated

How the community answered

(49 responses)
  • A
    2% (1)
  • B
    82% (40)
  • C
    2% (1)
  • D
    8% (4)
  • E
    6% (3)

Explanation