Which of the following is an input to direct and manage project execution?
The correct answer is B. Approved preventive action. Approved Preventive Action (B) is an input because it has already passed through the Integrated Change Control process and been authorized - Direct and Manage Project Execution receives approved items to act on, not items still awaiting a decision. A (Requested Changes) is…
Question
Which of the following is an input to direct and manage project execution?
Options
- ARequested changes
- BApproved preventive action
- CWork performance information
- DImplemented defect repair
How the community answered
(32 responses)- A3% (1)
- B84% (27)
- C3% (1)
- D9% (3)
Explanation
Approved Preventive Action (B) is an input because it has already passed through the Integrated Change Control process and been authorized - Direct and Manage Project Execution receives approved items to act on, not items still awaiting a decision.
A (Requested Changes) is wrong because it is an output of this process - requests originate during execution and flow out to Integrated Change Control for approval.
C (Work Performance Information) is wrong because it too is an output - it describes what actually happened (task status, costs incurred, etc.) and is generated as a result of executing the work.
D (Implemented Defect Repair) is wrong because "implemented" signals completion - it is an output confirming that a previously approved repair was carried out, not something fed into the process.
Memory tip: Use the approval lifecycle - Approved → Input → Implemented → Output. If the choice says "Approved," it's almost always an input to execution; if it says "Requested" or "Implemented," it's an output. The process takes in what's been authorized and produces what's been done.